Local Data Center Bans Push the AI Load Elsewhere
Voters limited data centers in 40 of 41 local races, then unseated Greg Abbott. The power demand did not vanish; it now sits on fewer grids.
40 of 41 local data center questions on November 3 went toward limits, according to Ballotpedia’s completed unofficial count, and Gina Hinojosa unseated Texas Gov. Greg Abbott by 706,700 votes. The queued load those votes were aimed at did not disappear with the returns.
Updated statewide totals on November 9 put Hinojosa at 5,232,690 votes (52.8%) and Abbott at 4,525,990 (45.7%), with Libertarian Pat Dixon at 148,140 (1.5%). Hinojosa, a five-term Austin lawmaker, becomes the first Democrat elected governor of Texas since Ann Richards in 1990 and the state’s first Latina governor. She has pledged a freeze on new approvals. The plants already in line still need power, water, and a county that will take them.
Forty of 41 Local Votes Went Against the Industry
No statewide data center question appeared on the November 3 ballot. The fight ran through city halls, townships, and county clerks. Ballotpedia logged 41 local data center measures that day in 10 states, part of a 2026 wave of 50 measures in 13 states. Ohio alone had 21 of the 41.
Voters favored tighter limits in 40 of those 41 contests. They passed 27 measures that restricted projects or stated opposition, and they rejected all 13 questions that would have helped a project move. The one exception was Harwood, North Dakota, where a proposed extra review of industrial sites, including data centers, failed 105 to 325.
By November 4, 47 of the year’s 50 measures had been decided, and 46 of them favored greater limits. Six had already gone that way earlier in the year. Three remain, including a December 15 vote in Mandan, North Dakota, on banning sites of 25 megawatts or more, and December 1 referendums in Clarksville, Arkansas, on industrial bonds for two campuses.
THE NOVEMBER 3 SCORECARD
| Place | What voters decided | Result |
|---|---|---|
| Alhambra, Calif. | Citywide prohibition | Yes 18,823 (84%) |
| Edgewater, Fla. | Ban on new centers | Yes 7,784 (77%) |
| El Dorado, Kan. | 10-year high-impact ban | Yes 2,972 (72%) |
| Emporia, Kan. | High-impact prohibition | Yes 4,346 (60%) |
| Ottawa, Kan. | Ban above 25 megawatts | Yes 2,882 (72%) |
| Granville, Ohio | Construction ban | Yes 2,015 (82%) |
| Grove City, Ohio | Voter approval on large loads | Yes 11,317 (55%) |
| Ashville, Ohio | EdgeConneX term sheet | No 1,469 (82%) |
| Wells, Maine | 180-day moratorium | Yes 5,818 (82%) |
| Harwood, N.D. | Extra industrial review | No 325 (76%) |
Five of the November 3 wins were full bans, in California, Florida, and three Ohio cities. Twelve were partial bans, including the three Kansas questions and eight Ohio caps, most of them drawn at 25 megawatts. Maine passed three 180-day moratoriums. Grove City was the closest of the large counts, at 55% to 45%, and it still raised the bar: voter approval for projects of 50 contiguous acres, more than 20 megawatts, or more than 500,000 gallons of water a day.
Emporia’s ordinance is narrower than a blanket veto and still bites. City ballot language defines a high-impact center as a site whose peak load above 10 megawatts or a daily water draw above 100,000 gallons, a net that also covers server farms, AI training halls, and crypto mines. The city has already warned that a court still has to decide whether the petition was legislative or administrative under Kansas law, so the 4,346-to-2,891 result does not close the file by itself.
Abbott Ordered a Pause That Did Not Hold
Abbott spent 2025 selling Texas as the place to build. At a November 14, 2025, appearance with Google chief executive Sundar Pichai in Midlothian, he called Texas “the epicenter of AI development” and said the country had to keep that work on U.S. soil. Campaign records compiled after the race show more than $9 million from data-center-related donors. When bills and water fights turned the issue toxic, he tried to slow-walk the same pipeline he had opened.
TEXAS PAUSE CALENDAR
- August 3, 2026: Directs the Public Utility Commission of Texas and ERCOT to audit large loads and hold Batch Zero interconnection notices.
- August 20, 2026: The commission approves ERCOT’s good-cause exceptions for that audit.
- September 21, 2026: Tells the Texas Commission on Environmental Quality to halt permits for data-center projects until the audit is done.
- September 22, 2026: TCEQ mails notices of preliminary approval to NRG’s Prairie Energy Center, VoltaGrid’s ABI-1 plant, and Nexus’s self-powered campus in Hubbard.
- October 19, 2026: FracTracker and Public Citizen publish a records review of post-pause TCEQ activity. TCEQ’s interim director writes that staff have paused applications that fall under the directive.
- December 10, 2026: ERCOT’s audit is due, covering about 300 proposed sites of 75 megawatts or larger in Batch Zero.
Abbott’s September 21 letter told TCEQ to halt all permits sought by data centers and said no other state agency should move on approvals until agencies had the facts on water and the grid. Press secretary Andrew Mahaleris later drew a thinner line. “No permits have been approved,” he said. “In line with the Governor’s directive, TCEQ has not taken and will not take any proactive actions related to the approval of data center permits.”
FracTracker, working with Public Citizen, still found 35 permitting actions after the directive: 14 permits fast-tracked or assigned to engineers, 11 stormwater coverages, 7 emissions certifications, and 3 public notices. Those steps included stormwater coverage for Crusoe’s Abilene campus and EdgeConneX’s Cedar Creek campus, and an October 6 generator application for Edged Energy in Dallas that an engineer had already given an initial review by October 9. Sam Law, FracTracker’s communications manager, said the pattern did “not signal an agency trying to pause.”
Hinojosa ran straight at that gap. She told voters Abbott’s freeze would expire with the audit and that “data center approvals will be back up and running in December, because Abbott is bought and paid for by global data center corporations.” On October 22 she went further on camera.
I will issue a moratorium, a ban, on all data center approvals.
Gina Hinojosa, Texas governor-elect, October 22 campaign video
She has said the freeze should last until the Legislature writes rules that give communities a seat, and she has pledged to have the Public Utility Commission freeze residential electric rates until high-load users pay for their own power. Abbott called her on election night and conceded. “There are still votes to be counted,” he said, “but mathematically, we’re not going to be able to win this election.”
A Write-In Mayor Beat the Name on the Ballot
The same pattern showed up in towns that never make a national map, which is where most of these buildings actually get sited. A yes vote in a city of 1,000 people can still kill a billion-dollar annexation, and a recall in a suburb of 23,000 can still unwind a land sale.
LOCAL RACES THAT FLIPPED
- Burgin, Kentucky: Write-in Joe Monroe beat the only printed name, council member George Hensley, 273 to 91 (75%) after Hensley backed annexation for Panattoni’s 950-acre Project Bluegrass.
- Yukon, Oklahoma: Voters recalled Mayor Brian Pillmore, who had supported selling about 185 acres at Route 66 and Frisco Road to Beltline Energy; challenger Joe Phillips won the Ward 3 seat. Vice Mayor Jeff Wootton had already resigned on June 6 after the petition named him too. Organizers put up 1,451 signatures, two more than the 1,449 required.
- Piqua, Ohio: Voters banned facilities over 25 megawatts and recalled a mayor and two commissioners who had backed a proposed 1,400-megawatt Meta campus.
- San Marcos, Texas: The city had already banned data centers on June 16 on a 4-3 council vote, becoming the first Texas city to do so, with council member Amanda Rodriguez pushing the amendment.
Monroe, who had been appointed interim mayor after a resignation and had to run as a write-in because the filing deadline had passed, said the margin surprised him. “I didn’t realize it would be by that kind of margin,” he said. “I’m thinking it probably had to do something with the data center.” Hensley was blunt in the other direction: “I wish now that we could have had the data center. I really do.”
In Emporia, the fight had already jumped the dais. Police arrested a school teacher for clapping during a data-center meeting, a clip that traveled farther than the ordinance text. A Virginia-based group, Defend US PAC, spent $38,531.68 against the Kansas questions, most of it on mailers. The bans still passed, 60% in Emporia, 72% in El Dorado, 72% in Ottawa.
Michael Whitesides, deputy communications director for Local Progress, a network of local officials that has spent the past year on this file, including members fighting data centers in Denver, read the night as a warning to anyone still taking the industry’s deal.
These midterms sent a clear message. People don’t want to see data centers in their backyards. Across the country, people do not see the promised benefit of these data centers, and the AI they power, playing out in their daily lives. They’re seeing basic goods and services get more expensive while these billionaire backed monstrosities take up space in their community, poison their air, and drive up their utility bills.
Michael Whitesides, deputy communications director, Local Progress
Where Does the Power Demand Go Now?
The ballots closed doors. They did not shrink the interconnection queue. In the August 3 letter that started the Texas audit, Abbott wrote that ERCOT was reviewing roughly 474 gigawatts of proposed new demand, more than five times the grid’s record hourly peak of 91,089 megawatts set on July 22, 2026, and that about 90% of those requests came from data centers.
THE LOAD STILL IN LINE
- Queued demand: About 474 gigawatts seeking to connect in ERCOT, roughly five times the July 22 peak of 91,089 megawatts.
- Share from data centers: About 90% of those requests, per Abbott’s letter.
- Audit window: ERCOT aims to file by December 10 on some 300 proposed sites of 75 megawatts or larger.
- Campuses already sized: Project plans put Stargate Frontier in Shackelford County at 1,820 megawatts and Nexus Hubbard, intended mostly to serve Anthropic, at 6,400 megawatts.
A local ban in Granville does not cancel a training run booked in 2027. It moves the megawatts to the next county that never put a question on the ballot, or to a behind-the-meter gas plant that never touches ERCOT’s queue. That is why Abbott’s TCEQ order mattered on paper: it was supposed to catch the self-powered sites too. The 35 later actions are why Hinojosa could campaign as if the pause were a prop.
The same displacement is already visible outside Texas. Ohio’s 21 measures were the densest cluster in the country, and Democrat Amy Acton won the governorship there on a “conditional moratorium” that would make operators cover 100% of utility costs and build with union labor. Incoming Democratic majorities in the U.S. House and Senate have already described a stack of bills on AI systems and data-center siting for January. That is not a national ban. It is a thicker local veto sitting on top of a load that still has to land somewhere.
Jim Bianco, who runs Bianco Research, put the political instruction in one line after the first returns: the measures are often non-binding, he wrote, but “politicians that want to remain employed as politicians are going to heed these messages.” The smarter read of the map is not that America switched off AI. It is that the remaining willing towns will take a larger share of the water, the diesel backups, and the rate cases.
Musk Spent $224 Million in Texas
Elon Musk treated Texas as the state that still wanted the buildings. Campaign finance records compiled after the election put his midterm spending at $474 million, including $224 million in Texas, where Tesla, SpaceX, and a planned $16.8 billion Terafab chip plant in Grimes County all depend on state cooperation. Abbott lost. Ken Paxton lost the Senate race to James Talarico. Democrats won the Texas House for the first time since 2002.
Musk stayed quiet through most of election night, then posted after the statewide races had been called.
Data centers in space looking pretty appealing right now
— Elon Musk (@elonmusk) November 4, 2026
“Data centers in space looking pretty appealing right now,” he wrote. A later post joked that his “election-interfering space lasers didn’t work this time.” Orbital compute is a real research line at SpaceX. It is also a tell. The constraint that beat his tickets is not a shortage of GPUs. It is land-use votes, water permits, and a residential ratepayer who now knows the acronym ERCOT.
Ad tracking counted $173 million in almost entirely negative data-center advertising nationwide this cycle. The industry still has a playbook for the counties that did not vote: tax abatements, NDAs, and a promise of jobs that, in Yukon, came bundled with a land sale a few hundred yards from houses. Whitesides’s warning was that the same playbook now has a recorded failure rate on election night.
Hinojosa’s Freeze Meets a Queue That Will Not Vanish
Hinojosa will not be sworn in until January, and Abbott’s audit clock still runs to December 10. She can issue a moratorium. She cannot delete 474 gigawatts of interconnection requests, or the gas plants already sized to feed them, with a press conference. The Legislature has to write the rate rule she wants, and home-rule cities that try to copy San Marcos will still face the preemption fight Rodriguez flagged the week of that 4-3 vote.
Hinojosa carried 37 of Texas’s 254 counties and still won by 706,700 votes because the large metros moved. Harris County went 63.5% to 35.0%. The data-center map is the inverse of that: the projects sit on cheap land and spare substations, which is why Burgin, Yukon, Emporia, and Piqua mattered more to the industry than a downtown precinct. Those places voted as if the promised jobs were not payment enough for the water and the wires.
The national build is still moving. New York is the rare state with a pause on construction. No federal siting ban passed on November 3. Developers will keep hunting counties that never printed the word “data center” on a ballot, and the remaining yes votes will carry more of the load. Hinojosa’s test is whether a Texas freeze becomes statute, or another September 21 letter that leaves the paperwork in motion while the queue waits for the next town that still says yes.
-
ENTERTAINMENT3 months agoRolex Made Drake the Daytona It Fights Jewelers Over
-
BUSINESS3 months agoTreasury’s First Iran Bank Shot Lands on an Ally
-
NEWS3 months agoInstinct’s $2.5 Billion Raise Still Binds the User as Agent
-
NEWS3 months agoCity’s £125m Enzo Deal Caps a £327m Midfield Rebuild
-
ENTERTAINMENT3 months agoRicky Gervais Wants Alley Cats to Run Until He Dies
-
NEWS3 months agoMeta’s Teen Settlement Leaves Chat Off the Clock
-
NEWS3 months agoCSIRTs Inherit Europe’s Missing security.txt Before Article 14
-
BUSINESS3 months agoBerkshire Anchors Alphabet’s Record Raise With a $10 Billion Check