NEWS
FAA Ground Stop Began on a Network It Does Not Own
The FAA ground stop began on a private L3Harris network, after one Arkansas router flooded 17 of 22 en route centers.
A new router at a remote Arkansas radio site flooded the FAA’s contractor-owned network on Nov. 13, forcing a nationwide ground stop of more than four hours. About 3,500 aircraft already airborne landed safely. Operators then canceled 12,462 flights that day.
The FBI has been examining the event. Officials say they have seen no cyberattack. The live system that failed still belongs to L3Harris, the vendor that has run it since 2002.
A Remote Router Halted Departures Across the Country
The Federal Aviation Administration says a technical problem hit at about 3:30 p.m. Eastern on Friday, Nov. 13. Old gear on the FAA Telecommunications Infrastructure, or FTI, became unstable when data flooded the network. The agency ordered a nationwide halt on departures as a safety step, then lifted it at 8:15 p.m. Eastern.
THE FRIDAY CLOCK
- November 13, 2026, about 3:30 p.m. ET: Data begins flooding FTI at a rate of 1,000 connection attempts every 4 to 5 seconds.
- Afternoon, Nov. 13: Instability reaches 17 of 22 Air Route Traffic Control Centers and several approach-control facilities.
- Nov. 13, during the halt: About 3,500 aircraft land. Life-saving, law-enforcement, and military flights keep going.
- Nov. 13, after the two sites are blocked: L3Harris cuts off El Dorado, Arkansas, and Amarillo, Texas, and the network steadies.
- November 13, 2026, 8:15 p.m. ET: The FAA lifts the ground stop. More than 8,000 flight operations resume that night.
FAA Administrator Bryan Bedford said no facility went fully dark. Some radio frequencies and radar feeds kept working, which is why every airborne jet made it in. The agency still stopped departures because it could not trust the rest of the picture.
L3Harris Owns the Wires Controllers Depend On
Transportation Secretary Sean P. Duffy named the contractor the next day. L3Harris, he said, has done this work for the FAA for more than 20 years, and L3Harris actually owns that network.
In at least one of our remote FAA locations, a contractor was doing routine maintenance to switch telecommunication lines from old copper wire and they were bringing it over to fiber. That contractor that does the work for us is L3Harris. They’re our legacy provider. They’ve been working for the FAA for over 20 years, and the network that we use at the FAA to control the airspace, L3Harris actually owns that network.
Sean P. Duffy, U.S. transportation secretary, Nov. 14 briefing
NOW: Air travel update from USDOT HQhttps://t.co/mbCWxKPm6O
— Secretary Sean Duffy (@SecDuffy) November 14, 2026
FTI is a private wide-area net that carries voice, radar, weather, and flight data among towers, radar sites, and en route centers. L3Harris describes the job as linking more than 4,400 FAA sites. Harris won the contract in 2002. The company, now L3Harris, still holds the live plant.
That ownership is the part the first-day talk about a “software update” left in the background. Early accounts described a patch that rebooted the private net and then crashed it. Duffy’s briefing, and the FAA’s own questions page two days later, pointed at a router swap during copper-to-fiber work at a radio site in El Dorado. The bureau’s role has been to look at that hardware, not to announce a crime.
L3Harris said it is supporting the FAA’s inquiry and takes the halt and its effect on travelers and airlines seriously. Duffy has not closed the file on how the box failed. He said the open choice is installer error or a faulty router.
Why a Site in Arkansas Reached 17 Centers
One new router at El Dorado, plus trouble at a radar site in Amarillo where a router had been changed about three weeks earlier, was enough to make 17 of 22 en route centers unsteady. Those centers guide high-altitude traffic between airports. When they wobble, the FAA stops departures rather than guess.
THE FLOOD ON FTI
- The rate: Legacy gear saw about 1,000 connection attempts every 4 to 5 seconds.
- The spread: Instability hit 17 of 22 en route centers and then several terminal approach controls.
- The cut: L3Harris blocked the two sites; the FAA also turned off the broadcast function on about 60 similar routers.
- The air: About 3,500 aircraft landed, and the FAA says every passenger on those flights arrived safely.
A thousand pings every few seconds is a lot for tired time-division gear. It is not a large flood for a modern network that can fence off a bad node. The failure that matters is containment. A radio site in southern Arkansas should not be able to shake most of the country’s high-altitude centers, and Friday showed that FTI still lets that happen.
Homeland Security Secretary Markwayne Mullin said new equipment and patches appeared to overwhelm older kit. The FAA, on Nov. 15, said the instability came from the legacy TDM system, not from the broader rebuild, and not from its SMART data tool. Bedford drew the same line. He said the agency spends about a billion dollars a year keeping the 1980s telecom net alive, and that crews are replacing some 2,000 Cisco 600 routers with Juniper units as ordinary upkeep, not as the $12.5 billion overhaul Congress has already funded.
This is also not a new shape of accident. In November 2009, a misconfigured replacement router during a similar fiber change disrupted flight-plan services nationwide. On Jan. 11, 2023, the Notice to Air Missions system failed after a contractor deleted files, and domestic departures were held about two hours. Friday lasted more than four hours and reached farther.
51 of 138 Systems Already Rated Unsustainable
After the 2023 halt, the FAA scored every air-traffic system it runs. The Government Accountability Office put those scores on the record in September 2024. Of 138 systems, the agency itself called 51 of its 138 systems are unsustainable, and 54 more potentially unsustainable, citing old functions and missing spare parts.
HOW THE FAA RATED ITS OWN SYSTEMS
| Rating from the 2023 assessment | Systems | Share |
|---|---|---|
| Unsustainable | 51 | 37% of 138 |
| Potentially unsustainable | 54 | 39% of 138 |
| Critical effect on safety or efficiency (subset of the 105) | 58 | 29 unsustainable, 29 potential |
| Especially concerning as of May 2024 | 17 | Some with no linked investment |
GAO said the FAA had been slow to fix the worst of that list. Some related projects were not due for 10 to 13 years. Four of the 17 most worrying systems had no investment tied to them at all. The watchdog’s first recommendation, still open in part, was that the FAA tell Congress how it is handling every unsustainable and critical system it finds in those yearly reviews.
Duffy used Friday to argue the other side of the same ledger. Congress, he said, has given him $12.5 billion, and he has replaced 69 percent of the copper communications with fiber. He listed new surface-awareness screens at 143 towers and 469 radio sites already converted. Bedford’s point still stands beside that list. The box that flooded FTI was sustainment on the old net, not a product of that down payment.
AT&T’s $74.3 Million Task Order Is Still Paper
The FAA has been shopping for the network that comes after FTI. That program is FAA Enterprise Network Services, or FENS, an internet-protocol net meant to carry operations and office traffic. Verizon won the first award in 2023. In August 2026 the agency changed course.
THE CONTRACT TRAIL
- 2002: Harris, now L3Harris, takes FTI and still owns the live plant.
- 2023: FENS, the successor net, is awarded as the path off FTI.
- August 11, 2026: AT&T gets a $74.3 million task order to start FENS planning and design, with Verizon moved to a supporting role.
- December 2028: The FAA’s stated deadline for its Brand New Air Traffic Control System, which FENS is supposed to underpin.
The August notice called the award an undefinitized single-award contract that could become a multi-billion-dollar deal for up to 15 years. The FAA said FTI can no longer support National Airspace System work or the new control system, and that a fresh contest would take at least 22 months and miss the 2028 date. Only the $74.3 million start-up order was funded at the time of that notice.
So the replacement has a prime contractor and a calendar. It does not yet carry radar and radio for the 22 centers. Until it does, copper-to-fiber work on L3Harris’s net is the path the FAA still walks, including in daylight at remote sites. After Friday, Duffy said that timing will be looked at again.
Airlines Canceled 12,462 Flights on Friday Alone
The FAA says operators canceled 12,462 flights on Friday, including 9,082 by major airlines, and that not every cancellation came straight from the halt. Aviation analytics firm Cirium counted about 1.5 million passengers booked to leave U.S. airports after 4 p.m. Eastern on some 11,000 flights, the window that sat under the stop.
Knock-on effects ran into the weekend as crews and aircraft sat in the wrong cities. FlightAware, the flight-tracking service, recorded nearly 6,700 U.S. cancellations and more than 9,100 delays on Saturday, then some 2,100 cancellations and 9,400 delays on Sunday. Duffy said on Nov. 15 that he expected a return to normal by Monday. Bedford had already warned that thousands of Saturday cancellations would remain while airlines rebuilt the schedule.
Medical, police, and military flights were not part of the halt. Duffy thanked controllers, pilots, cabin crews, and the passengers who waited. He also used the mess to press Congress for the rest of the money for a new telecom net, one he has said should not be owned by L3Harris.
The Probe Has the Routers and No Finished Cause
By Sunday the FAA had put names on the two sites and said the broadcast function was off on about 60 similar routers. Duffy said L3Harris had secured the units from El Dorado and Amarillo for deep testing at its Florida headquarters. Monday’s accounts had federal investigators taking possession of that same hardware. The open question is unchanged: a bad install, a bad box, or both.
WHAT WE KNOW
- The trigger window: Copper-to-fiber work at El Dorado, with a second site in Amarillo, lined up with the flood.
- The safety outcome: About 3,500 airborne aircraft landed, and the FAA reports no passenger injuries from the event.
- The cyber finding: The FAA, Duffy, and Mullin say they have no sign of a hack or an outside actor, and no link to the Microsoft outage that same week.
WHAT IS UNCONFIRMED
- The root cause: Duffy has not chosen between contractor error and a faulty router.
- The spread path: Officials have not published a full technical paper on why one remote node reached 17 centers.
- The next cutover: FENS remains a funded plan with a 2028 target, not the network controllers used on Nov. 13.
The FAA says it will rethink daytime swaps at small sites. Bedford still calls this year’s router swaps ordinary work on a 1G-era net. The routers sit in a Florida test lab, AT&T holds the paper for the next network, and every controller still talks over L3Harris wires.
-
ENTERTAINMENT3 months agoRolex Made Drake the Daytona It Fights Jewelers Over
-
BUSINESS3 months agoTreasury’s First Iran Bank Shot Lands on an Ally
-
NEWS3 months agoInstinct’s $2.5 Billion Raise Still Binds the User as Agent
-
NEWS3 months agoCity’s £125m Enzo Deal Caps a £327m Midfield Rebuild
-
ENTERTAINMENT3 months agoRicky Gervais Wants Alley Cats to Run Until He Dies
-
NEWS3 months agoMeta’s Teen Settlement Leaves Chat Off the Clock
-
NEWS3 months agoCSIRTs Inherit Europe’s Missing security.txt Before Article 14
-
BUSINESS3 months agoBerkshire Anchors Alphabet’s Record Raise With a $10 Billion Check